Have been
reading some old reports and it has made me realise I need to be more
descriptive of the location of the dig face. Today Pete was cementing in a step
sideways of about 1m to create a platform before the next downwards shaft
begins. John.
Survey
Saturday, February 5, 2022
Saturday 5th February 2022
John Cooper,
Nigel Graham and Pete Hann. 2 good mixes of cement loaded into 3 buckets. Pete
took the first one down which he had used up by the time John arrived with the
second. During moving the third one down below the Tunnel Nigel pulled a
boulder from the wall so John parked the cement whilst he removed the boulder
off Nigel and stashed it in the lower alcove. All three loads of cement used at
the bottom. Next week more capping and cementing. 1½ hours.