Survey
Saturday, March 23, 2019
Saturday 23rd March 2019
John
Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank, Jude Vanderplank and Barry
Wilkinson. Pete and Jude to the bottom with a mix of cement to do walling to
stack muddy gravel behind. The rest of us cleared spoil from the top stacking
space to the surface, 40 loads. Adrian and Jude swapped part way through so
Adrian could start capping. Once cleared we moved on down and made a good start
on filling it up again from the bottom stacking space, which is now clear. 3
hours. John.
Saturday, March 16, 2019
Saturday 16th March 2019
John
Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank, Jude Vanderplank and Barry
Wilkinson. Pete and Jude to the bottom to start stacking muddy gravel behind
walls whilst the rest of us cleared spoil from the bottom stacking space to the
top stacking space. Once cleared we moved on down and made a good start on
filling up the bottom stacking space again. Adrian did some capping towards the
end. 3 hours. John.
Saturday, March 2, 2019
Saturday 2nd March 2019
John
Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank and Barry Wilkinson. One
mix of cement sent to the bottom. Pete dug boulders out of the bottom and then
Adrian capped whilst the rest of us hauled their spoil up to the bottom
stacking space. Pete was then left with Adrian to use up the cement but they
also did more capping. The rest of us went out. 3 hours. John.