Saturday, January 26, 2019

Saturday 26th January 2019

John Cooper, Nigel Graham, Pete Hann, Wayne Starsmore and Adrian Vanderplank. One mix of cement sent to the bottom. Whilst Adrian capped rock at the bottom the rest of us moved it up to the lower intermediate stacking space. Then Adrian left the bottom to Pete who was able to cement up whilst the rest of us moved spoil from the lower intermediate stacking space to the upper intermediate stacking space. 3 hours. Pete’s flat front tyre then delayed us another hour. John.

Saturday, January 19, 2019

Saturday 19th January 2019

John Cooper, Nigel Graham, Pete Hann, Geoff Newton, Jake Tebbutt, Adrian Vanderplank, Jude Vanderplank and Barry Wilkinson. One mix of cement sent to the bottom. Whilst Pete and Adrian capped and cemented at the bottom the rest of us moved spoil from the lower intermediate stacking space to the surface. 48 loads removed. 2½ hours. John.

Saturday, January 12, 2019

Saturday 12th January 2019

John Cooper, Pete Hann, Adrian Vanderplank and Jude Vanderplank. One mix of cement sent to the bottom. Whilst Adrian capped rock at the bottom the rest of us moved it up to the lower intermediate stacking space. Then Adrian left the bottom to Pete who was able to cement up and also lift more rock out. The lower intermediate stacking space getting rather full now. 3½ hours. John.

Saturday, January 5, 2019

Saturday 5th January 2019

John Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank and Barry Wilkinson. One mix of cement sent to the bottom with Pete. To start Adrian capped rock at the dig face whilst the rest of us hauled it up to the lower intermediate stacking space. Then Pete cemented whilst the rest of us hauled from lower intermediate stacking space to the top intermediate stacking space. 3½ hours. John.

Saturday, December 29, 2018

Saturday 29th December 2018

John Cooper, Pete Hann, Adrian Vanderplank, Jude Vanderplank and Barry Wilkinson. Two mixes of cement sent to the bottom with Pete. The rest of us hauled 52 loads from the top intermediate stacking space to the surface. 2½ hours.John.

Saturday, December 22, 2018

Saturday 22nd December 2018

John Cooper, Nigel Graham, Pete Hann, Geoff Newton, Adrian Vanderplank, Jude Vanderplank and Barry Wilkinson. All working the bottom up to the top intermediate stacking space. Once this was full we left Adrian, Jude and Pete at the bottom whilst the rest of us moved on up and hauled 7 loads to the surface before the others came out. 2½ hours.John.

Saturday, December 15, 2018

Saturday 15th December 2018

John Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank, Jude Vanderplank and Barry Wilkinson. All working the bottom. Once Jude had cleared a bit of loose rock Adrian started capping his way on and down. Regular loads hauled up to the bottom stacking space. 2½ hours.John.