Survey
Saturday, September 24, 2022
Saturday 24th September 2022
John Cooper and Pete Hann. One mix
of cement taken in. Half used by Pete at the end and half by John further back.
Could have used a lot more. Outward draught still. 1½ hours. John.
Tuesday, September 13, 2022
Tuesday 13th September 2022
John Cooper, Wayne Starsmore,
Adrian Vanderplank and Jude Vanderplank. Took in a good mix of cement in 2
buckets. Adrian used 1½ building up walls at the end whilst John used ½ a
bucket cementing rocks in the roof of the approach rift (except for the ones
that fell out and were ably caught by Adrian!). 1½ hours. John.
Plan showing direction of Photos below. Plan by AV |
Photo 707 by AV |
Photo 712 by AV |
Photo 718 by AV |
Saturday, September 10, 2022
Saturday 10th September 2022
John Cooper, Adrian Vanderplank
and Jude Vanderplank. Drill and capping kit taken down. Initially John removed
a few small rocks from the end then Adrian capped a bigger one. These were
deposited at the little chamber stacking space. Jude then went to the face and
put a load of clatch behind Pete’s wall so he could build it higher. Good outward
draught. 2 hours. John.
Saturday, September 3, 2022
Saturday 3rd September 2022
John Cooper, Pete Hann, Adrian
Vanderplank and Jude Vanderplank. Full mix of cement taken down in 3 buckets.
Used by Pete building retaining walls at the dig face. Nice outward draught
still. Dig face now at least 4m below bottom survey station. 1½ hours. John.
Thursday, September 1, 2022
Thursday 1st September 2022
Richard Carey, John Cooper, Wayne Starsmore, Mike Thomas, Adrian Vanderplank
and Jude Vanderplank. The 19 loads hauled from the bottom to the bottom
stacking space became 18 when hauled from there to the Tunnel, remained at that
when hauled from the Tunnel to the bottom of the entrance shaft but became 10
rather heavier ones when hauled to the surface. 3 hours. John.