Survey
Saturday, November 27, 2021
Saturday 27th November 2021
John Cooper, Nigel Graham, Pete Hann and Adrian Vanderplank. Capping kit taken
in. Hauled spoil up from the bottom to the bottom stacking space until pretty
well full. Adrian and Pete not sure they have been digging in the right
direction at the bottom! There was an upward draught from the bottom to the
Tunnel and a very strong cold draught coming down the entrance as far as the
Tunnel! Where does the combined draught go? 2½ hours. John.
Saturday, November 20, 2021
Saturday 20th November 2021
John Cooper, Nigel Graham, Pete Hann, Wayne Starsmore, Adrian Vanderplank and
Jude Vanderplank. Hauled the spoil from the bottom ledge to the Tunnel then on
up to the bottom of the entrance shaft and finally 19 loads were hauled to the
surface. Very little draught but still a few drips. Adrian, Jude and Wayne had
a good look at the bottom trying to decide which direction to dig. 2½ hours. John.
Saturday, November 13, 2021
Saturday 13th November 2021
John Cooper, Nigel Graham, Pete Hann and Adrian Vanderplank. Took in capping
kit which Adrian used for about 10 holes before the battery was flat. However
Pete then went to the bottom and cleared loose spoil for another 90 minutes
until the bottom ledge was full. A bit of clatch stacked in the hole a couple
of metres up from the bottom. Pete says there is still lots of spoil available
but we need to clear the bottom ledge first. Gentle outward draught today and
not so drippy. 2½ hours. John.
Saturday, November 6, 2021
Saturday 6th November 2021
John Cooper, Nigel Graham, Pete Hann, Adrian Vanderplank and Jude Vanderplank.
One mix of cement, half sent in with Pete whilst the rest of us cleared 25
loads of spoil from the bottom of the entrance shaft to the surface. Then Jude
took the rest of the cement down to Pete whilst the capping kit was carried in.
Pete was wet and miserable so once he had used the cement up the capping kit
was carried out unused. 2½ hours. John.
Thursday, November 4, 2021
Thursday 4th November 2021
John
Cooper, Tom Williams, Wayne Starsmore, Adrian Vanderplank and Jude Vanderplank.
Tom and John to the dig face for a look and to retrieve the hammer. John then
broke up the largest rock on the bottom ledge before Adrian and Jude arrived.
We then hauled the rock from the bottom ledge up to the Tunnel. As large rocks
arrived John broke them up with another hammer that Adrian had retrieved from
Spider Hole on Tuesday. Once the bottom ledge was clear the spoil was moved on
up to the bottom of the entrance. It was a bit drippy tonight but no noticeable
draught. The scaffold frame was frozen over when we came out. 2½ hours. John.
Subscribe to:
Posts (Atom)